  1. A Project has the following time schedule

    Activity 1-2 1-6 2-3 2-4 3-5 4-5 6-7 5-8 7-8
    Duration(in days) 7 6 14 5 11 7 11 4 18

    Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

  2. Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity of the project given below and determine the Critical path of the project and duration to complete the project.

    Activity 1-2 1-3 1-5 2-3 2-4 3-4 3-5 3-6 4-6 5-6
    Duration ( in week) 8 7 12 4 10 3 5 10 7 4
  3. Solve the following linear programming problem graphically.
    Minimize Z = 200x1+ 500x2 subject to the constraints x1+2x≥ 10; 3x1+4x≤ 24 and x≥ 0, x≥ 0

  4. Solve the following linear programming problem graphically. Maximize Z = 60x1 + 15x2 subject to the constraints: x1 + x2 ≤ 50; 3x1 + x2 ≤ 90 and x1, x2 ≥ 0.

  5. The following table gives the characteristics of project

    Activity 1-2 1-3 2-3 3-4 3-5 4-6 5-6 6-7
    Duration (in days) 5 10 3 4 6 6 5 5

    Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.

*****************************************